Owners’ funds exposed by old legal actions

Unfinished legal actions could cost owners hundreds of thousands of dollars. Owners have little or no way of knowing what is happening in several expensive cases due to a lack of transparency by the current body corporate committee.

We list several cases where information has been concealed. These cases demonstrate a lack of transparency by the committee. Transparency means being open and honest about what you do. It’s a necessary step in fostering a culture of trust and is essential if owners are going to understand body corporate matters and successfully manage their apartment finances in an informed manner.

1. Removal and/or omission of records from the body corporate portal

The Southport Central Residential Community ‘Portal’, to which all owners have access, is
maintained by the Body Corporate Manager (BCM). You can access the portal on your
computer using the login information and password provided by the Body Corporate Manager or on your mobile using the Community app found on the Apple and Android App Stores.

The portal is effectively the only means by which owners can keep abreast of information
concerning the body corporate and is therefore of vital interest to all owners.

Until July 2023, owners could access the portal ‘Financials’ tab which included details of invoices submitted by, and payments made to, service providers. It allowed owners to see how our body corporate monies were being spent.

However, the Financials tab was removed after the Body Corporate manager was asked why access to invoices issued by the body corporate gardener had been blocked. Rather than unlock access to the gardener’s invoices, the BCM removed the Financials tab entirely (including the General Ledger) from the portal. The BCM has not responded to requests to re-instate the ‘Financials’ tab.

The ‘Financials’ tab could not have been removed without the knowledge of the committee.

The questionable actions previously included a payment of more than $50,000 for legal costs from body corporate funds. A legal company had provided services to the company CTS 35751 Investments Pty Ltd, not the body corporate and had erroneously invoiced the body corporate. It was paid by the Body Corporate Manager from body corporate funds and the payment apparently not disputed by the committee at the time. The body corporate was subsequently re-imbursed, but the entirety of this ‘error’ was never disclosed to owners and would not have been discovered save for the investigations of the Adjudicator.

In the Adjudicator’s words: “. . . there appears to have been a wholesale failure of even a basic level of appropriate and transparent decision-making and record-keeping over an extended period . . . . decisions to invest in the company, would appear. . . to have occurred in a procedural vacuum. There appears to be an extraordinary lack of records. There also appears to have been very little disclosure to owners as to what was being done.

If you don’t have access to the portal, or have forgotten your password, just email the Body Corporate Manager: cmg@completemanagementgroup.com.au Click here if you’d like to download the Adjudicator’s report.

2. The legal dispute with the Southport Central Commercial Body Corporate

In August 2019, a body corporate newsletter reported a long running dispute over the Residential Body Corporate arm of Southport Central paying a disproportionate share of expenses for the overall operation of the Southport Central site, which it shares with the Commercial arm, three Retail Body Corporates and Australia Fair. It was estimated that the Residential arm overpaid by $4 million. As a result, Residential withheld contributions to the common property electricity costs. Commercial then started legal proceedings.

Our committee told owners that they would be defending the proceedings and counterclaiming to claw back this money.  The newsletter concluded “We will endeavour to keep owners updated and believe this process will result in a significant reduction in levies.”

Despite repeated requests for information, successive committees did not update owners. However, in June 2022, a committee member told a committee Q&A session (attended by just 16 owners) that the legal dispute had settled along the lines that “neither party would pay anything to the other, and that both parties would bear their own legal costs”. This was despite Residential incurring legal expenses of about $150,000 which included engaging a solicitor, barrister and Kings Counsel. No further details were disclosed.

However, the matter hasn’t ended there and it seems our body corporate is still incurring legal costs. Committee meeting minutes dated 31 August this year says Southport Central Commercial action against Southport Central Residential is amongst legal matters noted as ‘current and ongoing’.

We don’t know what, if anything, has been achieved to date, and what exactly is the present status of this unresolved issue despite the spending of $150,000 of owners’ funds.

3. Unresolved debt issue with Metered Energy Holdings (MEH)

In October 2018, a body corporate newsletter reported that Southport Central Residential had changed its electricity and gas supplier from MEH to Flow Systems.

At the AGM in the same year, the body corporate approved the purchase of three gas hot water heater systems for up to $150,000, subject to a final valuation.

However, there is no available record that this purchase occurred, or confirmation as to who owns the hot water systems that Residential continues to use and maintain despite terminating the MEH contract as Southport Central Residential’s energy and gas supplier.

This raises the following questions:

  • Does the body corporate or MEH own the hot water systems?
  • Is the body corporate at risk of legal proceedings arising from this issue?

4. Unpaid invoices from Altogether Group estimated at $480,000

A dispute eventually arose between Flow Systems and our body corporate. In February 2021, the committee passed a motion not to pay invoices previously issued by Flow Systems (renamed as Altogether Group) and all future invoices for ‘common property’ electricity. The committee alleged that communications and negotiations between the supplier and the committee had been “unsatisfactory”, but no explanation was provided by the committee.

Common property electricity is for lighting across the complex, lifts, air-conditioning, carpark lighting and exhaust system, security system etc. As a result of the committee’s decision, invoices for common property electricity costing about $20,000 per month were not paid between February 2020 and February 2022. The two-year financial liability is calculated at about $480,000.

In March 2022, solicitors for Altogether Group, wrote to the Body Corporate concerning the outstanding accounts. The Body Corporate Manager denied receipt of such a letter but later paid an invoice from Herd Lawyers for “Professional fees for all attendances up to 5 April 2022” in response to a letter received from Hall & Wilcox regarding alleged outstanding accounts.

At the 8 June 2022 Q&A session, the committee denied there were unpaid invoices but offered no explanation as to why this could be so.  We all know that all electricity is not free and that Altogether has threatened debt recovery proceedings over these unpaid invoices, including interest and court costs.

The Committee has been asked to explain exactly where this matter stands but won’t say. Silence is NOT golden. Altogether have six years to recover the debt but do we want this issue hanging over our heads??

5. Removal of Altogether Group as our Energy Supplier

In what can only be described as dubious circumstances, the committee proposed a motion at the October 2021 AGM to replace Altogether Group with Locality Planning Energy Pty Ltd (LPE) for the supply and billing of electricity, hot water heating and cooker gas.

The motion is described as ‘dubious’ as owners were intentionally misled by the committee which presented a quote from LPE, but submitted a quote ‘attributed’ to Altogether, which had been prepared in January 2020 and was valid only until 30 June 2021. The expired quote used by the committee gave the impression that it had obtained two competitive quotes, when only one new quote had been sought, that being from LPE. At the very least, this was intentionally false and misleading, a slight of hand, the committee assuming that naive owners would not notice what had been done.

Despite several requests, neither the committee (nor the Body Corporate Manager who published the material) has not have provided an explanation as to why they engaged in such conduct.

Owners are invited to draw their own conclusions.

6. Investment Adviser’s Report

We have detailed the Body Corporate’s dubious action to spend almost $1.5 million of owners’ funds on buying four apartments in the name of a company established and operated by the then chairman of the body corporate committee and now under the control of the present Chairman. Not only was the activity ethically questionable, the body corporate’s own financial adviser had warned about the plan.

The committee had told owners and a Body Corporate Commission Adjudicator that it had relied on the investment advice provided by Innovative Financial Solutions (IFS).

The IFS report was initially provided to the committee in June 2020, but was not posted publicly on the community portal until just a few days before the 2020 AGM. The timing was too late for most owners to read and consider the report before they voted at the 2020 AGM.

Importantly, the IFS report did NOT advise the committee to invest in residential property, as they had claimed. The report cautioned against investing in real estate.  It warned about “a lack of diversity in investments”. It said: “alternative investment vehicles and asset classes are not being addressed in detail in the light of your decision to invest in residential property”/ The IFS report said it was unable “to draft an actual investment strategy document”; and concluded that “you are still heavily exposed to residential property”. The Body Corporate Adjudicator concluded: “I do not consider that the decision to invest in the Company was in accordance with the IFS advice.”

It seems this highly relevant report was removed from the community portal because it did not support the Committee’s investment scheme. In September 2022, the Adjudicator ordered that the body corporate “divest itself of its current shareholding CTS 35751 Investments Pty Ltd and recover the funds invested in that company”.

A copy of the Innovative Financial Solutions (IFS), ‘Statement of Advice’ can be found here.

Residents denied access to sinking fund forecast

Owners denied access to sinking fund forecast

The purpose of a body corporate sinking fund is to collect a small amount of money from all owners each year to meet anticipated major expenditure over the next 10-year period.

The sinking fund forecast (SFF) estimates the cost to cover future expenditure for the replacement and/or maintenance and repair of building components at the end of their expected life – and calculates what owner levy contributions will be required each year to cover those expenses when they become due.

The importance of the SFF is obvious, but few people know ‘what it looks like’ and how it provides a ‘window into the future’ of the body corporate finances.

The SFF is not set in concrete because it is based on estimates, made by experts, but there will be occasions when components fail prematurely or when a vital component must be replaced, and/or the current cost of replacement far exceeds the estimate made in the last SFF.

An example can be seen here in the case of the 2018 estimate of the costs replacement of the scheme intercom system, which enables visitors to contact residents at the entrance to their respective tower, and for the resident to remotely release the front door and activate the lift call button to enable the visitor to reach the resident’s apartment.

In 2018 this cost was estimated at $121,471 whereas Motion 10 (on the 2023 AGM agenda) shows competitive quotes between $408,204 and $539,572. The body corporate is not required to strictly follow the SFF, but it must adapt to unforeseen demand on financial resources.

The sinking fund forecast provides a blueprint and a ‘window into the future’ through which owners can see what is ‘reasonably’ expected to occur over the coming year or years both in terms of repair and maintenance of building components and the associated costs.

The easiest way to understand the scope of the SFF is to take a look at the attached SFF prepared by Seymour Consultants for our scheme in 2018.

For reasons not apparent, the sinking fund forecast has not been posted on the body corporate portal where it could be perused by owners.

Angry gardeners

Our ailing gardens demand better care

Gardens across the Level 3 Pool Deck and Level 12 have progressively deteriorated over recent years. Many established plants/shrubs and palms have died off or are looking increasingly distressed.

The pool deck gardens are an important feature of our complex, which if properly maintained, will add considerably to its attractiveness and value.

The gardens are desperately in need of professional attention. The current contractor, a one-man band, does not purport to possess any horticultural qualifications, which are essential if the gardens are to be rejuvenated and maintained to an appropriate standard.

‘Thrive Horticultural’, are a team of professionals with qualifications in horticulture, relevant experience and the firm is a member of Nursery and Gardening Industry Association of QLD.

Last year we proposed a motion at the AGM that we engage Thrive Horticultural to perform the groundskeeping works at the scheme on a month-to-month agreement. This would enable us to assess the quality of the service being provided. No other contractor was proposed for this position.

The Budget proposed by the committee for 2023 included $85,000.00 for garden/lawn maintenance. The Thrive quote was $79,552 per annum (or $6630 including GST per month). We need a better solution than the current one to restore our gardens.

A voting machine

Electronic voting is easier for owners

At the 2017 AGM the body corporate voted overwhelmingly in favour of electronic voting
‘when the technology became available’. Compliant electronic voting systems became available in 2019 and in 2020 Body Corporate legislation was amended in 2020 to simplify the introduction of electronic voting to ‘allow voters to cast a vote using a computer, smartphone or computer tablet.

However, at the 2021 AGM, the committee, rather than encouraging owners to vote and engage in body corporate decision making, proposed a motion without explanation to revoke the 2017 motion, which unfortunately passed. This intentionally limits the opportunity for owners to vote where they cannot attend meetings. Instead, they must download, complete, scan and email their voting papers (which is not always possible) or rely on postal services which are expensive and unreliable – especially for owners living or travelling interstate or overseas.

This complicated process is eliminated entirely when an owner can ‘cast a vote using a computer, smartphone or computer tablet’.

Southport Central Residential is languishing behind many other bodies corporate. Electronic voting is convenient, cost-effective and improves transparency and accuracy in vote counting. It will enable YOU to vote from anywhere. It is not compulsory, and you can still vote by traditional means or vote in person at the AGM, if that is your preference.

VOTE YES to introduce electronic voting and let owners vote online at all body corporate general meetings.

Flooding in Tower 1 at Southport Central Residential

Replacing Aquatherm pipes could cost a fortune

Catastrophe struck tower 1 on 20 February 2023 when a polypropylene Aquatherm water pipe on level 10 burst and unleashed a torrent of hot water that collapsed the level 10 foyer ceiling, and flooded apartments, stairwells, lift shafts and common areas on levels 10 and 9. Lifts, electrical boards, security systems and lighting were taken out and one lift took months to return to service.

Residents on upper floors unable to navigate dozens of staircases were initially stranded. The volunteers who brought them supplies/assisted those who could navigate the stairs deserve our gratitude.

Eight months on, and the body corporate committee has offered only limited information about the progress of repairs and the estimated cost of repairs. Two building managers reports in March and April 2023 describe action to be taken and provide a schedule for reparation works. But that’s it. That’s not good enough.

The body corporate manager, who maintains all the body corporate records, when requested to provide a copy of the ‘expert reports’ obtained by the committee replied: “We are not aware of the documents you refer to.”

The Chairman of the Committee has ignored a similar request for information. Why the secrecy?

We still don’t know whether the damage to common and personal property will be covered by the body corporate insurance or to what extent. We don’t know what steps have been taken to prevent or minimise the prospect of a second pipe failure. We don’t know if insurance would cover a second event, particularly if we’re slow to replace the Aquatherm system.

We do know that in 2019, US$23.5 million was needed to repair a US jail’s extensive Aquatherm system which was under a decade old.

We do know that in February 2016 a Brisbane body corporate made application for an adjudicator’s order to authorise spending to replace the Aquatherm hot water line at a cost
above the committee’s spending limit and that numerous bodies corporate including Watermark Kangaroo Point, Marquis On Main Beach,  Signature Park Apartment
Merrimac, Regatta Riverside Toowong, Ocean Pacific Broadbeach, Metropolis On Ann Brisbane CBD, Tempo Apartments West End, and Quest Riverpark Central Brisbane CBD have all replaced their Aquatherm piping.

We do know that Aquatherm, a German plumbing invention of the 1980s, is expected to fail if the pipes are NOT PROPERLY clamped, became prone to failure if certain
chemicals are in the water such as chlorine, and if the water is particularly hot, as is common in Australian installations.

There had been problems with the hot water pipes at Southport Central in the year before the pipe burst. The Mantra Building Manager’s report of 31 August 2022 advised of significant leaks in the Aquatherm hot water feed pipes in Tower 1, and noted it had been suggested that a secondary hot water feed line be installed using copper pipes to do away with the Aquatherm (polypropylene) pipes to avoid a potential major flooding incident.

At the AGM in late 2022, owners approved a committee motion to set aside $600,000 of sinking fund money to urgently replace “the failing Aquatherm pipes”.

A year on from that, and some extensively water damaged apartments and infrastructure on levels 9 and 10 are still being repaired. It appears a secondary hot water feed line will need to be installed to replace on all residential levels. The
installation includes cutting core holes in the concrete fire stair landings to reroute the hot water feed line.

Insurance usually covers only replacing like-with-like, but it seems the proposal is to not only reroute the hot water feed line but replace all Aquatherm pipes with copper
pipes from the rooftop down through residential levels 39 to 9, and through the foyer ceiling spaces in each level.

Aquatherm pipes are installed in Tower 1 only, but ultimately all owners contribute to the sinking fund and cost of repairs beyond that covered by insurance.

Beyond what insurance will cover, all owners in Southport Central Residential will bear the cost of this work and must be provided with access to all relevant reports, which can be simply posted on the Portal maintained by the Body Corporate Manager) detailing the scope of works, estimated cost and timeframe for this work to be carried out.

We know it is not possible to predict when and if further failure of the existing Aquatherm pipes will occur, but all Tower 1 owners and their tenants must be told what steps, if any, have been taken pending replacement of the existing Aquatherm pipes to minimise the prospect of a further flooding event. Their safety is at stake.

Should an Aquathern pipe burst on a much higher level, it could have an even more widespread, catastrophic effect and send water cascading down dozens of floors with massive cost consequences.